Transmission Network for Evacuation of Power from BBMB Projects. The power generation at BBMB Power stations is being evacuated through BBMB Power Transmission Network system,
running into 3751.96 Circuit Km. length of 400 KV, 220 KV, 132 KV and 66KV transmission lines and 24 EHV Sub-Stations.
Transmission Network
TRANSMISSION LINES
|
Line Voltage (KV)
|
Name of Line
|
Single Ckt. (S/C) or Double Ckt. (D/C)
|
Length (Km)
|
Date of Energisation / Commissioning
|
1
|
400
|
Dehar-Panchkula
|
S/C
|
125.00 |
19.09.1979 |
2
|
400
|
Panchkula -Panipat
|
S/C
|
155.00 |
LILO at Panchkula on 31.03.2015
|
3
|
400
|
Dehar-Rajpura
|
S/C
|
129.00
|
27.01.1990 |
4
|
400
|
Rajpura-Bhiwani
|
S/C
|
212.80
|
LILO at Rajpura on 25.06.2016
|
5
|
220
|
Ganguwal-Dhulkote
|
D/C
|
112.00
|
25.11.1962
|
6
|
220
|
Dhulkote-Panipat
|
D/C
|
130.00 |
1962
|
7
|
220
|
Panipat-Narela I & II
|
D/C
|
56.90 |
7/1962
|
8
|
220
|
Panipat-Narela III
|
S/C
|
58.00
|
02/07/1979 |
9
|
220
|
Narela-R/Road Delhi
|
D/C
|
22.00
|
1962
|
10
|
220
|
Pong-Jalandhar I & II
|
D/C
|
97.50 |
Pong-Jalandhar I-30.06.1978
Pong-Jalandhar II-26.01.1978 |
11
|
220
|
Pong-Dasuya IV
|
S/C
|
40.00
|
06.10.1982 |
12
|
220
|
Jalandhar- Dasuya IV
|
S/C
|
56.00
|
06.10.1982
|
13
|
220
|
Jamalpur-Jalandhar
|
D/C
|
70.00
|
Jamalpur-Jalandhar I-19.12.1969
Jamalpur-Jalandhar II-16.10.1969
|
|
14
|
220
|
Bhakra-Jamalpur
|
D/C
|
86.4 |
18.12.1968 |
15
|
220
|
Jamalpur-Sangrur
|
D/C
|
78
|
30.01.1969 |
16
|
220
|
Sangrur-Hisar
|
D/C
|
139.00
|
31.01.1969 |
17
|
220
|
Hisar-Bhiwani I & II
|
D/C
|
57.80 |
07.07.1970 & 24.01.1976 |
18
|
220
|
Bhiwani-Dadri I &II
|
D/C
|
34.70 |
17.06.1988 |
19
|
220
|
Bhiwani-Dadri III & IV
|
D/C
|
34.45 |
16.03.1990 & 9.10.1990 |
20
|
220
|
Ballabgarh-Badarpur I & II
|
D/C
|
24.73 |
17.11.1968 & 3.5.1971 |
21
|
220
|
Bhakra-Ganguwal I & II
|
D/C
|
21.00
|
Line relates to Generation 12/1968
|
22
|
220
|
Bhakra -Ganguwal III & IV
|
D/C
|
22.00
|
Line relates to Generation
III-19.7.1980
IV-12/1968
|
23
|
220
|
Bhakra_GanguwalCkt V
|
S/C
|
22.00
|
Line relates to Generation 12/1968
|
24
|
220
|
Samayapur-Ballabgarh I & II
|
D/C
|
4.23 |
Samayapur-Ballabgarh I 9.4.1989 & Samayapur-Ballabgarh II 31.3.1989 |
25
|
220
|
Samayapur-Ballabgarh
|
S/C
|
5.50 |
25.05.1988 |
26
|
220
|
Dehar-Ganguwal
|
D/C
|
56.00
|
Line relates to Generation
Dehar-Ganguwal I-6.10.1977
Dehar-Ganguwal II-30.09.1977
|
27
|
220
|
Dadri-Ballabhgarh
|
S/C
|
119.89 |
25.01.1976 |
28
|
220
|
Samaypur-Dadri
|
S/C
|
118.396 |
25.05.1988 |
29
|
220
|
Bhakra (L)-Ganguwal
|
S/C
|
22.00
|
Line relates to Generation 19.07.1980
|
30
|
220
|
Sangrur-Barnala
|
S/C
|
38.14 |
08.02.1976 |
31
|
220
|
Barnala-LehraMohabbat
|
S/C
|
38.56 |
11.05.1987 |
32
|
220
|
Lehramohabbat-Bathinda
|
S/C
|
27.93 |
08.02.1976
|
33 |
220
|
Ganguwal-Jagadhari
|
S/C
|
158.65 |
01.01.1978 |
34
|
220
|
Panipat-Dadri
|
S/C
|
115.00
|
25.09.1978 |
35
|
220
|
Kurukshetra-Panipat
|
S/C
|
77.63 |
01.01.1978 |
36
|
220
|
Jagadhari-Kurukshetra
|
S/C
|
48.30 |
01.01.1978 |
37
|
220
|
Dadri-Mohindergarh II
|
S/C
|
40.116
|
21.6.2003, Line relates to HPGCL
|
38
|
132
|
Ganguwal-Kotla
|
D/C
|
|
Line Relates to Generation
|
39
|
66
|
Chandigarh-Dhulkote
|
D/C
|
45.00
|
02.1.1955 & 17.3.1967
|
40
|
66
|
Bhakra (L)-NayaNangal
|
D/C
|
9.00
|
Line Relates to Generation
|
41
|
66
|
Pinjore-Chandigarh
|
S/C
|
12.00
|
1976, Relates to HPGCL
|
42
|
66
|
Pinjore-Chandigarh
|
S/C
|
18.00
|
1976, Relates to HPGCL
|
43
|
66
|
Bhakra(L)-NayaNangal
|
S/C
|
9.00
|
Line Relates to Generation
|
Note:- Record of Line Data from Sr. No. 37-43 is not related to this office.
Sub Stations
Sr. No. |
Name of Substation
|
Date of commissioning
|
Historical importance
|
|
a) 400 KV Sub-Stations
|
1. |
400 kV Panipat
|
12/1976
|
It is the first 400kV BBMB substation constructed by BCB under Beas Project in 1969. There are Six nos. 400kV bays, twenty two 220kV bays, ten 132kV bays. Connected to Dehar Power House through 400kV Dehar-Panchkula- Panipat Single Circuit line and Power
Grid Dadri through 400kV Panipat-Dadri Single Circuit line. |
2. |
400 kV Bhiwani
|
17/06/1988 |
Second 400kV BBMB Substation constructed by BCB in 1983. Connected to Dehar Power House through Dehar-Rajpura-Bhiwani line and to Power Grid through 400kV Bhiwani-Bhiwani PGCIL Line. |
b ) 200 KV Sub-Stations
|
1. |
220 kV Ballabhgarh
|
17/11/1968 |
This sub-station is connected with Badarpur Thermal Power Station through 2 nos. 220KV Ballabgarh-BTPS circuits, with Samaypur through 3 nos. 220KV Ballabgarh-Samaypur circuits, with Charkhi Dadri through 1 no. 220KV Ballabgarh Charkhi Dadri circuit and
with HPGCL, Faridabad Thermal through 66kV line. |
|
2. |
220 kV Samaypur
|
09/1988
|
Created for dispersal of Power from Singrauli and Rihand Super Thermal Power Station. Connected with 400kV PGCIL through four 400/220kV, 315MVA ICTs and with Faridabad Gas Power Plant (CCGT) through 220kV Double circuit line.
|
|
3. |
220kV Narela
|
1977
|
The sub-station was constructed by BCB in the year 1972, and was completed and commissioned in the year 1977 by extending 2 Nos. 220 KV Buses from Grid Sub-Station of DVB (now DTL). The Sub-Station was handed over to BBMB on 05.09.1977 and is one of the
radial Sub-Stations of BBMB.
|
|
4. |
220 kV Delhi
|
1958
|
The sub-station was constructed by BCB under left Bank Power Project in 1950. It supplies power to DTL through 33kV feeders for which DTL pays rentals. Roof Top Solar Plant (80kWp) was installed on 29.01.2019.
|
|
5. |
220kV Kurukshetra
|
12/1977 |
This Sub-Station was constructed by BCB under Beas Project and handed over to BBMB for operation and maintenance during Dec-1977. This Sub-Station is connected through 220 KV Single Circuit line to Jagadhari and Panipat. |
|
6. |
220 kV Jamalpur
|
18/11/1968
|
The Substation was first energized on 18.11.1968 after being constructed under Bhakra Right Bank Project when the power from Right Bank Bhakra was brought to this area through 220KV Bhakra –Jamalpur double circuit line. It feeds Punjab area.
|
|
7. |
220kV Jalandhar
|
16/10/1969
|
The Sub-Station was erected under Bhakra Right Bank Project by BCB and was energized on 16.10.1969 on commissioning of 220KV Jamalpur-Jalandhar Line to carry Power of Bhakra Complex from 220KV Sub-Station, BBMB, Jamalpur to Jalandhar. It feeds Punjab
area.
|
|
8. |
220 kV Hisar
|
23/02/1969
|
This substation was constructed by BCB under Bhakra Right Bank project and commissioned on 23.02.1969. It feeds Haryana and some parts of Rajasthan.
|
|
9. |
220 kV Sangrur
|
1968-69
|
This Sub Station was constructed by BCB under the scope of Bhakra Right Bank Project and commissioned during the year 1968-69. The Sub Station was further augmented during the year 1976, under the scope of Beas Project. It feeds Punjab area.
|
|
10. |
220 kV Barnala
|
11/05/1987 |
This Sub Station was constructed by BCB under the Scope of Beas Project and commissioned on 11.05.1987 and handed over to BBMB on 01.10.1987. The 220KV Grid Sub Station Barnala is the only Switching Station. |
|
11. |
220 kV Dhulkote
|
1955 |
This sub-station was originally commissioned during 1955 on 132KV voltage level from Ganguwal – power house and subsequently with coming up of Bhakra Left Bank Power House, it was energized on 220KV voltage level during 1962. It is the
first intermediate power take off substation on the 220KV Double Circuit Ganguwal-Delhi Transmission line emanating from Major inter linking substation, Ganguwal. It feeds Haryana and Chandigarh. |
|
12. |
220 kV Jagadhari
|
31/05/1978 |
This Sub-Station was constructed by B.C.B. under Beas Project Stage-II and commissioned on 31.05.1978 and was subsequently handed over to BBMB on 31.05.1978 for operation and maintenance. This Sub-Station is the first intermediate power
take off sub-station on the 220KV single circuit Ganguwal – Jagadhari – Kurukshetra - Panipat – Narela Line. |
|
13. |
220 kV Charkhi Dadri
|
18/10/1977
|
This Substation was constructed by BCB under Beas Project Scheme and completed on 18.10.1977 after the commissioning of the bays and were taken on 22.10.77 by BBMB. It feeds Haryana and Rajasthan areas.
|
|
14. |
66 kV Chandigarh
|
1955 |
The Sub Station was constructed in 1955 under Bhakra Left Bank Project by the P.W.D. Electricity Branch for catering the power demand of Chandigarh and its surroundings. Thereafter it remained with PSEB and was taken over by BBMB from
PSEB during 1967, immediately after re-organization of Punjab and Haryana. |
|
|
|